COSHH assessments for subcontractors: a practical guide

What a COSHH assessment needs to cover for construction subcontractors, how to use safety data sheets, and how it fits into your RAMS.

COSHHUpdated 5 min read

By Ramvio team, Guides

Sealants, adhesives, resins, cement, paints, cleaning chemicals, and the dust you make cutting materials: most trades work with something that could harm health. COSHH assessments are how you show you've thought about it. This guide covers what they need, using the regulations and the HSE's guidance, for subcontractors and the contractors who check their paperwork.

What COSHH is

COSHH stands for the Control of Substances Hazardous to Health Regulations 2002 (opens in a new tab). They require employers to control exposure to hazardous substances to protect workers and others. The HSE's COSHH pages (opens in a new tab) and its legal guidance, L5 (opens in a new tab), explain them in detail.

Substances covered include chemicals and products with hazard classifications, and also dusts, fumes and vapours created by the work. In construction, dusts such as respirable crystalline silica (from cutting concrete, brick and stone) and wood dust are common causes of serious ill health.

Who must do the assessment

Regulation 6 of the COSHH Regulations (opens in a new tab) puts the duty on the employer. An employer must not carry out work liable to expose employees to a hazardous substance unless they have made a suitable and sufficient assessment of the risk, and put in place the steps it identifies.

So a subcontractor's COSHH assessments are the subcontractor's responsibility, for the products and processes they use. A tier-2 contractor or principal contractor checking them doesn't take over that duty, but will usually want to see them before work starts, often as part of the RAMS.

If the employer has five or more employees, the significant findings and the control steps must be recorded.

What the assessment must consider

Regulation 6(2) lists what the assessment must consider, where relevant. In practical terms:

  • What the substance is and how it can harm. Its hazardous properties, and the health effects the supplier describes.
  • The safety data sheet. Information from the supplier, including the safety data sheet.
  • Exposure. How workers could be exposed (breathing it in, skin contact, swallowing), how much, and for how long.
  • The circumstances of the work. The amount used, where (indoors, confined spaces, poorly ventilated areas), and the task.
  • High-exposure activities. Such as cleaning out equipment or maintenance.
  • Exposure limits. Any workplace exposure limit that applies to the substance.
  • Controls. The effect of the control measures you'll use.
  • Combined exposure. Where people are exposed to more than one substance at once.

Using safety data sheets

The safety data sheet (SDS) is the starting point, not the assessment itself. A common mistake is attaching the SDS and calling it a COSHH assessment. The SDS tells you about the product. The assessment tells you how your work, on this site, will be done safely with it.

From the SDS, pick out:

  • the hazard statements and pictograms
  • the first aid measures
  • the exposure controls and personal protection the supplier recommends
  • handling, storage and disposal
  • what to do about spills and fire

Check that the SDS is for the actual product and supplier you're using, and that it's current. Suppliers of hazardous products should provide one; if you don't have it, ask your supplier or merchant.

Controls: the order matters

Regulation 7 of COSHH (opens in a new tab) requires exposure to be prevented, or where that isn't reasonably practicable, adequately controlled. The regulation sets out the protection measures in order of priority:

  1. Work processes, systems, engineering controls and equipment. For example, choosing a less hazardous product, or a method that creates less dust.
  2. Control at source. For example, on-tool extraction, water suppression or ventilation.
  3. Personal protective equipment. Only where adequate control can't be achieved by the other measures, and in addition to them.

A COSHH assessment that goes straight to "wear a mask and gloves" will usually be questioned. Show what you've done higher up the list first. Where respiratory protection is used, it must be suitable for the substance and the task, and tight-fitting masks need a face-fit test for the person wearing them.

Information and training

Under regulation 12 of COSHH (opens in a new tab), employers must give workers who could be exposed suitable information, instruction and training. That includes the names of the substances and the risks they present, any relevant exposure limits, and access to the safety data sheets. In practice, brief the COSHH assessments with the RAMS, and make sure the safety data sheets are available on site.

Keeping assessments current

COSHH assessments must be reviewed regularly, and straight away if they may no longer be valid, the work changes significantly, or monitoring shows it's needed (regulation 6(3)). A new product, a different supplier or a change of method are all good reasons to review. See how often RAMS should be reviewed for the wider picture.

Fitting COSHH into the RAMS

The simplest approach is one COSHH assessment per substance or dust-producing process, referenced from the RAMS for each task that uses it. That way:

  • the RAMS stays readable
  • the same assessment can be reused across tasks, as long as it still fits the work
  • a reviewer can see at a glance which substances the task involves

Our guide to what a RAMS should include shows where COSHH sits among the other sections.

Drafting COSHH assessments faster

Ramvio drafts a COSHH assessment for each substance ticked for a task. When you upload the supplier's safety data sheet, the draft is based on it; when you don't, it's clearly marked to be checked against the SDS. A competent person reviews and approves every one. If that would save your team time, ask for early access.

This guide is general information, not legal or professional advice. RAMS and COSHH assessments must be prepared and approved by a competent person.

Write job-specific RAMS in minutes

Ramvio drafts RAMS from the task, the site and the principal contractor's rules. Your competent person reviews and approves every one.

Register your interest