What should a RAMS include?

What a RAMS needs to cover for UK construction work, where the duties come from in law and CDM 2015, and what principal contractors look for.

RAMSUpdated 6 min read

By Ramvio team, Guides

A RAMS (risk assessment and method statement) is the document a contractor uses to show how a specific piece of work will be done safely. Principal contractors ask for one before work starts, and many will not let a contractor on site without an accepted RAMS.

This guide sets out what a good RAMS covers, where the underlying duties come from, and what principal contractors tend to check. It is written for contracts managers and H&S managers who write RAMS, or check the ones their subcontractors send in.

The term "RAMS" doesn't appear in health and safety law. What the law requires is the thinking behind it:

A method statement is the usual way of showing how the work has been planned. Combining it with the risk assessment, as a RAMS, is common practice in UK construction rather than a format the law sets. Our guide to RAMS vs risk assessment vs method statement explains the difference in more detail.

What principal contractors look for

A principal contractor has its own duty, under regulation 13 of CDM 2015 (opens in a new tab), to plan, manage and coordinate the construction phase. Reviewing contractors' RAMS is one of the ways many principal contractors do that.

In practice, they want to see that the RAMS:

  • is written for this site and this task, not copied from another job
  • follows the site rules and the construction phase plan, which regulation 12 (opens in a new tab) says must set out the site's health and safety arrangements and site rules
  • meets their own minimum standards, which are often stricter than the legal minimum (for example, requiring a particular glove cut level, or banning certain access equipment on their sites)
  • names real people, real equipment and real competencies

What to include in a RAMS

There is no single official template, and every principal contractor has its own preferences. Most good RAMS cover the following.

The job and the site

  • The site name and address, the principal contractor, and your company's details
  • A clear description of the scope of work, and where on the site it happens
  • Dates or programme, and working hours if they matter (for example, noisy work)
  • The revision number and date, and who wrote and approved it

The sequence of work

Set out the work step by step, in the order it will be done. This is the method statement part, and it's where generic RAMS usually fall down. A reviewer should be able to picture the job: how materials arrive and are stored, how they are lifted or moved, how the work area is set up, the task itself, and how the area is left.

Hazards, risks and controls

For each significant hazard, say who could be harmed, how, and what you'll do about it. Controls should follow the hierarchy: remove the hazard where you can, then reduce it, and treat personal protective equipment as the last line of defence. Common construction hazards include work at height, lifting operations, manual handling, hazardous substances, dust, noise, vibration and live services.

Many RAMS score each risk before and after controls. If yours do, make sure the scoring method is explained and the scores make sense: a reviewer will notice if every risk is "low" after controls whatever the task.

Write job-specific RAMS in minutes

Ramvio drafts RAMS from the task, the site and the principal contractor's rules. Your competent person reviews and approves every one.

Register your interest

People and competence

Under regulation 15(7) of CDM 2015 (opens in a new tab), a contractor must not appoint anyone to work on site unless they have, or are getting, the skills, knowledge, training and experience for the task. A RAMS should show this, for example:

  • the supervisor for the work, and how they can be contacted
  • the cards and training the task needs, such as CSCS, IPAF or PASMA where relevant
  • any people who need extra supervision, such as apprentices or new starters

Plant, equipment and substances

List the plant and equipment you'll use, and how you know it's safe: current inspections, thorough examinations for lifting equipment, and who is trained to use it. For any hazardous substances, include or refer to a COSHH assessment for each one. Our guide to COSHH assessments for subcontractors covers what those need.

Emergencies and welfare

Regulation 15(9) of CDM 2015 says the information given to workers must include the procedures to follow in serious and imminent danger. In a RAMS, that usually means:

  • first aid arrangements and who the first aiders are
  • the nearest A&E with its address, checked for the site, including that the hospital has a 24-hour emergency department
  • how to raise the alarm, and the assembly point
  • any rescue plan the task needs, for example for work at height or confined spaces

Briefing and sign-off

A RAMS only works if the people doing the job know what's in it. Regulation 15(8) requires contractors to give workers appropriate supervision, instructions and information. A briefing record, signed by everyone who will do the work, shows that the RAMS has been explained to the people it protects.

Keeping it usable

A RAMS is a working document, not a file to fill a folder. A few habits help:

  • Keep it as short as the job allows. A 60-page RAMS for a two-day task is hard to brief and easy to ignore.
  • Write for the people doing the work. Plain words, no padding, and the key controls easy to find.
  • Update it when things change. A change of method, equipment or location usually means a new revision. See how often RAMS should be reviewed.

Who writes and who approves

The contractor doing the work is responsible for its risk assessment and method. In practice, RAMS are often drafted by a supervisor, contracts manager or H&S adviser, then reviewed by a competent person in the contractor's business before they go to the principal contractor. The principal contractor's review doesn't take that responsibility away from the contractor.

Whatever tools you use to draft it, a competent person who understands the work must check the content against the actual job and sign it off.

Writing RAMS faster

Ramvio drafts job-specific RAMS from the task, the site's rules and the principal contractor's documents, so your competent person starts from a draft that fits the job rather than a blank template, then reviews and approves it. If that would help your team, ask for early access.

Further reading: the HSE's guidance on CDM 2015 (opens in a new tab), its legal guidance L153 (opens in a new tab), and its pages on managing risks and risk assessment (opens in a new tab).

This guide is general information, not legal or professional advice. RAMS and COSHH assessments must be prepared and approved by a competent person.