How often should RAMS be reviewed?

When a RAMS needs reviewing, what the law says about reviewing risk assessments, and the changes on site that should trigger a new revision.

RAMSUpdated 5 min read

By Ramvio team, Guides

A RAMS that was right on day one can be wrong by week three. The method changes, a different crew turns up, the scaffold moves, or the principal contractor changes a site rule. Knowing when to review a RAMS, and doing it properly, keeps it useful and keeps your team protected.

What the law says

There's no fixed review period for a RAMS in UK law. The duty to review comes from the risk assessment behind it.

Regulation 3(3) of the Management of Health and Safety at Work Regulations 1999 (opens in a new tab) says a risk assessment must be reviewed by the person who made it if:

  • there is reason to suspect it is no longer valid, or
  • there has been a significant change in the matters it relates to

and that any changes the review shows are needed must be made.

For hazardous substances, the COSHH Regulations 2002, regulation 6(3) (opens in a new tab) go further: a COSHH assessment must be reviewed regularly, and straight away if it may no longer be valid, the work has changed significantly, or exposure monitoring shows it's needed.

So the legal answer is "whenever it might no longer be right, and regularly for COSHH". In practice, most contractors and principal contractors also set a fixed review period on top.

Fixed review periods

Many principal contractors ask for RAMS to be reviewed at set intervals, and some set an expiry date after which a RAMS must be reviewed and re-approved before work continues. Three months is common. No law sets a review period, so always check the site's own requirement.

A fixed period is a sensible backstop. It catches the slow drift that nobody notices: a supervisor who has left, a piece of plant that has been replaced, a card that has expired. But it isn't a substitute for reviewing when things change.

Changes that should trigger a review

Review the RAMS, and issue a new revision if needed, whenever any of these change:

  • The method. A different sequence, a new way of lifting, or a change to how the work area is set up.
  • The location. Moving to a different level, elevation or area of the site with different hazards.
  • Plant and equipment. Swapping a mobile tower for a MEWP, hiring different plant, or changing tools.
  • Substances. A new product, or a different supplier's version of the same product. Check its safety data sheet and update the COSHH assessment.
  • People. A new supervisor, a new crew, or workers without the competencies the RAMS relies on.
  • Site conditions. Weather, ground conditions, nearby work by other trades, or changes to access and welfare.
  • Site rules. A change to the principal contractor's construction phase plan or minimum standards.
  • Something going wrong. An accident, near miss or dangerous occurrence on the task, or a similar task elsewhere.
Warning:

Don't move a RAMS to another site

A RAMS written for one site shouldn't be reused on another without a full review. The site rules, access, emergency arrangements and principal contractor's requirements will all be different.

How to review a RAMS properly

A review is more than changing the date on the front page. A good review:

  1. Walks the task. Check the RAMS against what is actually happening on site, ideally with the supervisor and the people doing the work.
  2. Checks every section. Scope, sequence, hazards, controls, people, plant, substances and emergency arrangements.
  3. Records what changed. Keep each revision, with what changed and why, rather than overwriting the old one. If something goes wrong, you'll need to show which version was in use.
  4. Gets approved again. The changed RAMS goes back through your own approval and, where required, the principal contractor's.
  5. Is briefed again. The people doing the work need to know what has changed. Under regulation 15(8) of CDM 2015 (opens in a new tab), contractors must give workers appropriate instructions and information; a new briefing record shows that happened.

Version control

Keeping old revisions matters. A RAMS is a record of how you planned the work, and if there's ever an investigation, the question will be what the RAMS said at the time. A simple approach:

  • give every RAMS a revision number and date
  • never edit an approved revision; create a new one
  • record who reviewed and approved each revision
  • keep superseded revisions, marked as superseded, for as long as your records policy says

How long to keep records depends on your company's policy, your insurer and your contracts. Some records have their own legal retention periods, such as health surveillance records under COSHH, so check before you delete anything.

Reviews and the principal contractor

If your RAMS has been accepted by a principal contractor, tell them when a review changes it. Under regulation 15(3) of CDM 2015 (opens in a new tab), contractors must follow the principal contractor's directions and the relevant parts of the construction phase plan, and the principal contractor needs to know what's actually happening on site to coordinate the work of different trades. Many principal contractors ask for revised RAMS to be resubmitted before the changed work starts. Check the site's procedure, and don't start the changed work until the new revision has been accepted where that's required.

Who should review it

The review should be done by someone competent to judge the risks of the work: often the person who wrote the RAMS, the supervisor, or your H&S adviser. Whoever does it, the approval of the reviewed RAMS stays with a competent person in your business. For what a complete RAMS covers, see what should a RAMS include.

Making reviews easier

Reviews get skipped when they're hard to track. Ramvio keeps every revision, records who approved it, and reminds you before a RAMS reaches its review date, so your team knows which RAMS are current on which site. A competent person still reviews and approves each one. If that sounds useful, ask for early access.

Further reading: the HSE's guidance on managing risks and risk assessment (opens in a new tab) and on COSHH (opens in a new tab).

This guide is general information, not legal or professional advice. RAMS and COSHH assessments must be prepared and approved by a competent person.

Write job-specific RAMS in minutes

Ramvio drafts RAMS from the task, the site and the principal contractor's rules. Your competent person reviews and approves every one.

Register your interest