RAMS vs risk assessment vs method statement: what's the difference?

A risk assessment, a method statement and a RAMS explained: what each one is for, which the law requires, and how they fit together on site.

RAMSUpdated 5 min read

By Ramvio team, Guides

"Send us your RAMS" is one of the most common requests on a UK construction project. But the three terms involved, risk assessment, method statement and RAMS, are often used loosely. Knowing what each one is for makes it easier to write documents that do their job and get accepted first time.

The short answer

  • A risk assessment identifies the hazards in the work, who could be harmed and how, and the controls you'll use. The law requires one.
  • A method statement describes how the work will be done, step by step, with those controls built in. The law doesn't use the term, but it's the usual way to show the work has been planned.
  • A RAMS puts the two together in one document for a specific task on a specific site.
Risk assessment, method statement and RAMS compared
DocumentWhat it answersRequired by law?
Risk assessmentWhat could go wrong, who could be harmed, and how is it controlled?Yes: an assessment is required, and recorded if you employ five or more
Method statementHow exactly will the work be done safely, in what order, by whom?Not by name, but contractors must plan and manage their work
RAMSBoth, for one task on one siteNo, it's an industry format; principal contractors often require it

Risk assessment

The legal duty comes from regulation 3 of the Management of Health and Safety at Work Regulations 1999 (opens in a new tab). Every employer must make "a suitable and sufficient assessment" of the risks to their employees, and to other people affected by their work, so they can identify the measures they need to take. Self-employed people have a similar duty. If the employer has five or more employees, the significant findings must be recorded.

A risk assessment looks at:

  • the hazards: things that could cause harm, such as work at height, moving vehicles or silica dust
  • who could be harmed and how, including people who aren't your employees, like other trades or the public
  • the controls in place, and whether more are needed
  • who is responsible for each control

The HSE's guidance on managing risks and risk assessment (opens in a new tab) explains the process in plain terms.

A risk assessment on its own can be fairly general. A company might have one for "working at height using mobile towers" that covers its usual way of working. That's useful, but it doesn't tell a principal contractor how a particular job on their site will be done.

Method statement

A method statement turns the assessment into a plan for the actual job. It sets out:

  • the scope of work and where it happens
  • the sequence of the work, step by step
  • the people, their roles and their competence
  • the plant, equipment and materials
  • how the controls from the risk assessment are applied at each step
  • emergency arrangements

There's no regulation called "method statement". But regulation 15 of CDM 2015 (opens in a new tab) requires every contractor to plan, manage and monitor the work under their control so it's carried out, so far as is reasonably practicable, without risks to health and safety. A method statement is the usual written evidence that this planning has happened. The HSE's legal guidance on CDM, L153 (opens in a new tab), explains what the contractor duties mean in practice.

RAMS

A RAMS is simply the risk assessment and method statement for a specific task, presented together. Combining them has practical advantages:

  • the reader sees each hazard and its control in the context of the step where it arises
  • there's one document to review, approve, brief and keep
  • it's easier to check that every significant hazard has a control in the method

Most principal contractors in the UK ask for RAMS in this combined form before a contractor starts work. Some provide their own template; others accept any format that covers their requirements. Our guide to what a RAMS should include goes through the sections in detail.

How they fit together

A useful way to think about it:

  1. Your company's general risk assessments cover the activities you do regularly.
  2. For a specific job, you write a RAMS: the risk assessment for that task on that site, and the method that controls it.
  3. The RAMS also has to fit the principal contractor's construction phase plan and site rules, which regulation 12 of CDM 2015 (opens in a new tab) requires them to set out.
  4. Where the task involves hazardous substances, it refers to the COSHH assessments for each one (see our COSHH guide for subcontractors).

The common mistake is sending the general risk assessment, or a RAMS from a previous job, when the principal contractor asked for a site-specific RAMS. That's one of the most frequent reasons RAMS are sent back: see why principal contractors reject RAMS.

Do I need all three?

For most construction work under a principal contractor, yes, in practice:

  • the risk assessment is a legal duty
  • the planning behind a method statement is a legal duty under CDM 2015
  • the RAMS format is what the principal contractor will usually ask for

For small, low-risk tasks, a short RAMS is fine, and often better than a long one. What matters is that it is suitable and sufficient for the actual work, and that the people doing the work understand it.

Getting it right without starting from scratch

Writing a site-specific RAMS for every task takes time, which is why copy-and-paste RAMS are so common. Ramvio drafts a RAMS from the task, the site rules and the principal contractor's requirements, and a competent person in your team reviews, edits and approves it. If you'd like to try it, ask for early access.

This guide is general information, not legal or professional advice. RAMS and COSHH assessments must be prepared and approved by a competent person.